The transformation works of La Rambla enter the final phase
January 15th. 2026
On January 14, 2026, the Barcelona City Council organized an informative session on the transformation works of La Rambla.
The session, which was attended by the director of Urban Development, Àlex Montes, the general director of BIMSA, Ricard Font, and the head of the Rambla Office, Aina Pedret, took place in the Ernest Lluch room at the headquarters of the Ciutat Vella District.
We provide you with a brief summary of what was presented and you will find the presentation pdf attached.
Phases of action
GÒTIC Phase: sidewalk opening. Initial forecast of 11 months. Executed in 12 months due to archaeology and services in B2
RAVAL Phase: sidewalk opening. Initial forecast of 10 months. Opening to traffic at the end of May 2026
CENTRAL Phase: Paving of the central promenade, planters, and services. Preliminary start on November 17, the rest from January 19, 2026
Total term: 32 months
Section impacts
You will find a map in the attached pdf.
The Rambla Space is a consultation space for doubts related to the reform and is available to you from Monday to Friday from 10:15 to 18:15 at the Palau de La Virreina (La Rambla, 99).